Today in Kourou, French Guiana, Mr Fredrick Engstr¿m, ESA Director of Launchers, Mr Michel Courtois, Deputy Director-General of CNES and Mr Jean-Marie Luton, Chairman of Arianespace signed the document formally handing over Ariane launch complex ELA-3 from ESA to Arianespace.

Representing an investment of some 800 million ECU, ELA-3 is by far the

largest installation built by ESA under the Ariane-5 development

programme. CNES was responsible for its design, construction and

operation during cryogenic main stage testing and the first two qualification

flights, in its capacity as prime contractor for the development of the

Ariane-5 launcher and launch facilities. Arianespace will now take over

responsibility for ELA-3 operations, including launcher integration and

launch operations, final payload preparation, management and

maintenance of facilities, insurance, safety and quality control, in addition

to the similar responsibilities it has discharged since 1986 for the ELA-2

complex dedicated to Ariane-4.

Preparations for the hand-over of ELA-3 management responsibility to

Arianespace had been under way for some years, with the progressive

integration of Arianespace engineers and technicians into the CNES

teams, to ensure that personnel training was properly completed following

execution of the first two Ariane-5 qualification flights. Particular attention

has been paid to the industrial set-up in order to secure a coherent and

optimised structure meeting ELA-2 and ELA-3 operations & maintenance

requirements. To that end, Arianespace is contracting the same European

companies which have hitherto been working under CNES contracts.

Twelve firms (from Belgium, France, Germany, Italy and Spain) provide

some 250 specialists under operations & maintenance contracts for the

fluids and mechanical systems, computerised checkout systems, power

supply and air conditioning.

Arianespace also draws on the Guiana Space Centre's support services

for Ariane-5 launch campaigns, on the same basis as for Ariane-4

launches. These support activities, managed by CNES on behalf of ESA

with European contractors, include coordination of overall launch range

operations, ground and inflight safety, tracking and telemetry stations,

meteorology, telecommunications, operations & maintenance for payload

preparation facilities and logistical facilities.

Main features of ELA-3

The ELA-3 complex covers a 15 square km (3 x 5 km) area of land located

close to Ariane-4 launch complex ELA-2 and 25 km north-west of Kourou.

It is designed to handle a launch rate of eight to ten Ariane-5 launches per year at one month intervals. The duration of a standard launch campaign

will be 22 working days, once the necessary learning phase is over.

The basic ELA-3 design differs from that of earlier Ariane launch

complexes in that there is no mobile servicing gantry or umbilical mast in

the launch zone. This enhances the availability of the launch facilities and simplifies the launch zone itself, reducing its vulnerability in the event of an accident.

Construction work on ELA-3, which started in 1988, involved some two

million man-hours and sixty European companies providing the requisite

engineering design, construction and test expertise in the following areas:

infrastructures, power supply, air conditioning, mechanical structures,

specialised tooling, ground-to-launcher connections, cryogenic and

conventional fluids, computerized checkout systems, inspection, etc.

ELA-3 consists of two zones:

the launcher preparation zone, comprising:

the launch control centre, located in a 2700 square m protected

enclosure which is designed to withstand the impact of falling launcher

elements and includes:

two independent launcher checkout rooms, just one of which is fitted out currently,

one checkout room for ground utilities (power, air conditioning, fire detection, alarm systems),

three rooms for payload checkout;

the launcher integration building, 58 m high with an air-conditioned

interior of 80 000 cubic m where the solid-booster, main and upper

stages and vehicle equipment bay are assembled on a mobile launch

table. Assembly, electrical and tightness checks will be performed here

in a 13-day cycle, before roll-out to the final assembly building;

the final assembly building, 90 m high with an air-conditioned interior

of 123 000 cubic m where payloads are mated with their flight adapters,

encapsulated inside the fairing and hoisted onto the launcher. Assembly

of the launcher's upper section, the associated electrical checks and

upper-stage filling with propellants will be carried out here in a

8-day cycle before the launcher is finally rolled out to the launch

zone some hours prior to lift-off;

the launch zone, for final countdown and lift-off, comprising:

a solid base interfacing with the launch table, including the cryogenic

propellant (liquid oxygen/hydrogen) feedlines and launcher checkout

umbilical connections. It also has a wind dampening shield and four

lightning-conductor towers,

three separate flame trenches (one for the Vulcain engine and one for

each booster),

a 90 m high water tower with a storage capacity of 1500 cubic m for

table cooling and noise dampening on lift-off,

– connection facilities for the mobile cryogenic storage tanks,

a 310 square m gaseous hydrogen burn-off pool.

ELA-3 also comprises a 4 km twin railtrack for launcher roll-out and one

mobile launch table with an integrated umbilical mast (a second table is

due to be delivered in 1998). Each launch table weighs 870 tonnes

unladen, supports the launcher throughout its preparation campaign and

is fitted with a two-part 58 m high umbilical mast. The launch table/launcher

assembly, weighing 1500 tonnes, is towed by truck from the final assembly

building to the launch zone. In-transit power, ventilation and air-

conditioning requirements are met by a special servicing unit, while a

damper is used to absorb the energy generated by the action of the wind

on the launcher.

Between 1994 and 1996, the ELA-3 facilities were satisfactorily used for a

series of main stage firing tests, which ground-qualified the stage and the

ground facilities. The first two Ariane-5 qualification campaigns (501 and

502) proceeded without major technical problems regarding the ELA-3

ground facilities, which, with the improvements made to ange facilities

(safety, telemetry, downrange stations, etc.), are therefore considered as

qualified.

With the ELA-3 launch complex, other Ariane-5-dedicated production and

test facilities built during the development phase are being handed over

by ESA to the industrial operators at the Guiana Space Centre:

the Guiana propellant plant, for mixing and casting the large solid-

propellant booster segments, handed over in 1990 to Regulus, a joint

subsidiary of Fiat Avio (Italy) and SNPE (France);

the booster integration building, handed over in 1992 to

Europropulsion, a joint subsidiary of SEP (France) and Fiat Avio;

the booster preparation building, handed over in 1996 to Aerospatiale

(France);

the booster teststand, used for seven development and qualification

tests between 1993 and 1995 and to be used for quality-control test

firings on production units;

the liquid hydrogen plant, built and operated by l'Air Liquide (France).